Corona Virus

Corona and contract law: Disruption of contracts

The coronavirus is forcing countries around the world to take drastic measures to counter the spread of the virus. This is having a serious impact on contract law. Many of these measures mean that contracts can no longer be fulfilled by at least one party. The cases affected are countless.

The limitation period for freight claims – the exception is the rule for freight compensation claims!

The freight business is mass business. The industry is therefore reliant on being able to “shelve” individual freight orders promptly. For this reason, international freight law, which aims to protect the freight industry, provides for a much shorter limitation period for transport law claims than the standard limitation period. It is not easy to answer the question of which limitation period for freight claims actually applies in a specific case. 1, 2 or 3?

Law on the limitation of contract terms – Good night, freedom of contract ?

In mid-August 2019, it became public that the law on limiting contract terms (“Cost Trap Act”) was at an advanced stage.

truck on a highway through the grasslands area of eastern Washington, USA.

The limitation period under transport law according to § 439 HGB

The limitation period under transport law in accordance with Section 439 HGB is only one year from delivery, which is significantly shorter than the 3-year standard limitation period in Section 195 BGB.

Construction crane stands on the background of the sky. Construction site. Tower crane.

Construction contract law: Remuneration for “additional services” in lump-sum price contracts

The remuneration for “additional services” in lump-sum price contracts in the event of supplementary offers from the contractor is complex. In principle, the additional remuneration demanded as a result of the supplement must be derived from the (plant) construction contract concluded between the parties.

globe ball on table with laptop and notebook,travel concept.

The action for a negative declaratory judgment to prevent a foreign action

If a dispute arises with a foreign business partner, e.g. regarding alleged claims arising from a contract, it is advisable from the point of view of the German contracting party to think about possible procedural scenarios at an early stage in case an agreement fails. If, contrary to the agreements made, it is to be expected that the foreign partner intends to file a lawsuit in the home country, you should immediately consider filing a preventive so-called negative declaratory action at the agreed German place of jurisdiction.

Construction worker in protective uniform shaking hands with businessman in hardhat at construction

Construction contract law: Global lump sum contract or detailed lump sum contract?

In (plant) construction projects, disputes under construction contract law about the remuneration ultimately owed to the contractor carrying out the work are not uncommon. Is there a lump sum contract or not? The distinction between a global lump-sum contract and a detailed lump-sum contract can regularly cause major difficulties.

Businessman sleeping at office

Procedural law: The inactive expert witness

The inactive expert witness is a major dilemma for those affected. The legislator has certainly recognized this and, with a reform of the law on expert witnesses with effect from 15.10.2016, has anchored quite relevant tightening in civil procedure law.

E-Mail service

The delivery of contractual declarations by e-mail

E-mail is a practical way of sending (contractual) declarations and/or documents to a business partner.

Classical columns close up architecture

Federal Court of Justice clarifies the legal term “use assumed under the contract”

In its ruling of March 20, 2019, the Federal Court of Justice (BGH) provided practical clarification on the understanding of “use assumed under the contract”.