Arbitration Clauses in Plant Construction

The general contractor sends you the subcontract. The project sounds promising, the scope is right, and the technical requirements are feasible. On one of the last pages is the dispute resolution clause: All disputes shall be finally settled by three arbitrators in accordance with the ICC Rules of Arbitration, with London as the seat of arbitration and English as the language of the proceedings. The general contractor explains that this is how it’s worded in the main contract with the end customer; they’re simply reproducing it here.

You’ll realize what this clause means two years later, when you have to go to court to collect your final invoice for three hundred thousand euros. Arbitration clauses are standard in international plant construction between the end customer and the general contractor, and they often make sense in that context. However, if the same clause is passed down the project chain to subcontractors and component manufacturers—who have significantly lower contract volumes and different interests—the assessment is quite different.

Why the arbitration clause is being passed down the chain

The general contractor wants to establish uniform rules for dispute resolution throughout the supply chain. If the general contractor is bound by arbitration with respect to the end customer, it wants to be able to seek recourse against its subcontractor under the same framework. Otherwise, the general contractor will be sued before an arbitration tribunal in London and will have to sue its subcontractor in the Stuttgart Regional Court, facing different procedural rules, different methods of taking evidence, and the risk of conflicting outcomes. There is no third-party notice that would prevent this between an ICC arbitration and state court proceedings.

That is a legitimate concern, but simply mirroring the clause only partially resolves it. An arbitration clause with identical wording does not make the subcontractor a party to the arbitration proceedings between the end customer and the general contractor. Without coordinated clauses and the consent of the parties involved, there will still be two separate arbitration proceedings. For the subcontractor, what matters in any case is whether the clause is acceptable to them personally.

How Much Arbitration Costs a Subcontractor

Arbitration is significantly more expensive than proceedings before state courts. In addition to attorneys’ fees, there are the fees charged by the arbitration institution and the arbitrators’ fees; the state pays the judges at the regional court. Under the ICC Rules of Arbitration, if the amount in dispute is three hundred thousand euros, the expedited procedure applies automatically—in which, as a rule, a sole arbitrator decides the case, even if the clause provides for three arbitrators. However, this applies only if the parties have not excluded it, and even then, the costs are significantly higher than the court fees of a regional court. If the proceedings are conducted in English, translation costs are added for the contract, correspondence, technical documents, and witness testimony. In a plant construction dispute involving extensive documentation, this constitutes a separate cost category.

Advance Payment and Reimbursement of Expenses

Added to this is the issue of advance payment. The ICC generally requires both parties to contribute equally to the advance payment. If the general contractor fails to pay its share, the subcontractor must cover it; otherwise, the subcontractor’s claim is deemed withdrawn. Ultimately, the arbitral tribunal decides on the reimbursement of costs at its discretion, taking into account, above all, the outcome of the proceedings (Section 1057(1) of the German Code of Civil Procedure [ZPO] for German arbitration seats; comparable provisions apply in the arbitration rules). The winning party is thus generally reimbursed for its costs, but only at the end of the proceedings and to an extent that is more difficult to predict than the cost allocation under Section 91 of the German Code of Civil Procedure (ZPO).

Cost Risk Associated with Smaller Claims

For a subcontractor or component manufacturer seeking to recover a final invoice in the mid-five-figure or low-six-figure range, the costs of arbitration may be disproportionate to the amount in dispute. The arbitration clause then effectively acts as a waiver of the right to sue, even though the claim exists. The general contractor who included the clause may not have intended this.

No appeal

An arbitral award is final. There is no second instance. If the place of arbitration is in Germany, the arbitral award may be set aside only pursuant to § 1059 of the German Code of Civil Procedure (ZPO), for example, due to an invalid arbitration agreement, a violation of the right to be heard, material procedural errors, or a violation of public policy. An incorrect application of the law or an erroneous assessment of the evidence does not fall under these grounds. Where the place of arbitration is London, English law applies, which likewise permits a review of the merits only within narrow limits.

For the general contractor, with a dispute amount of twenty million euros, this is a calculable risk; he handles the proceedings from the outset with the necessary effort. The subcontractor, who loses his claim of over three hundred thousand euros on the first and only attempt, no longer has any opportunity to have an error corrected. In state court, he would have had the option to appeal to the Higher Regional Court, which would have conducted a full review of the application of the law and, in cases of concrete doubt, reexamined the findings of fact (Section 529(1)(1) of the German Code of Civil Procedure (ZPO)). This second review is particularly valuable in technically complex disputes.

Enforceability

The main argument in favor of arbitration clauses in international business is enforceability. Under the 1958 New York Convention, an arbitral award is enforceable in 172 contracting states. There is no comparable network for judgments issued by national courts outside of Europe. For a general contractor seeking to enforce a judgment against an end customer in Saudi Arabia or Kazakhstan, the New York Convention is therefore indispensable.

However, the subcontractor’s contracting party is the general contractor, who is often based in Germany or, in any case, within the EU. A German judgment against a general contractor in Munich or Hamburg is enforceable as a matter of course; a judgment against a general contractor in France or the Netherlands is enforceable under Article 39 of the Brussels Ia Regulation without requiring a declaration of enforceability there. The argument supporting the arbitration clause in the main contract does not apply in this context.

The situation is different if the general contractor is based outside the EU or if the subcontractor supplies goods directly to a foreign client. In such cases, the arbitration clause may also be beneficial for the subcontractor. It is a mistake to include it in the main contract without addressing this issue.

Confidentiality

The confidentiality of arbitration proceedings is cited as an advantage. It is not a given, however: The DIS Rules of Arbitration require the parties to maintain confidentiality (Art. 44 DIS Rules of Arbitration), whereas the ICC Rules of Arbitration impose this obligation only on the arbitrators. Under the ICC Rules, the parties are bound by this obligation only if they have agreed to it.

To the extent that confidentiality exists, it primarily benefits the general contractor in the supply chain. The general contractor does not want its contractual structures and terms to become public knowledge, nor does it want other subcontractors to learn which of its clauses an arbitration tribunal has rejected. For the subcontractor, however, the public nature of government proceedings can serve as a means of leverage. A general contractor whose payment practices are discussed in a public hearing behaves differently than one who operates under the protection of confidentiality.

What a Subcontractor Should Do During Contract Negotiations

The arbitration clause is negotiable, even if the general contractor presents it as a requirement of the main contract. It is virtually impossible to remove it later. According to the case law of the Federal Court of Justice, an arbitration clause in general terms and conditions does not, in and of itself, unreasonably disadvantage the contracting party (BGH, judgment of January 13, 2005 – III ZR 265/03). If the subcontractor nevertheless files a lawsuit in state court, the claim will be dismissed as inadmissible upon objection by the general contractor (Section 1032(1) of the Code of Civil Procedure (ZPO)).

Agreement on a State of Jurisdiction

If the general contractor is based in Germany or the EU, the argument regarding enforceability does not apply. The subcontractor should then propose a jurisdiction clause in favor of a state court, which offers lower costs, the right to appeal, and public hearings. In response to the objection that the general contractor needs the arbitration clause for recourse, it can be argued that merely mirroring this provision only partially solves the problem.

Place of Arbitration, Language of the Proceedings, and Rules of Procedure

If the subcontractor must accept the arbitration clause because the general contractor is based outside the EU or the subcontractor lacks sufficient bargaining power, the specific terms of the clause are crucial. If the place of arbitration is in Germany, German arbitration law applies, and German courts decide on any annulment. A place of arbitration at the end customer’s place of business—with whom the subcontractor has no dealings—primarily results in additional costs. The language of the proceedings should be the same as that of the contract itself and the technical documentation. Furthermore, expedited proceedings must not be excluded. Under the ICC, expedited proceedings apply automatically unless the clause provides otherwise; under the DIS, they apply only if agreed upon.

Mediation or Conciliation as a Preliminary Step

A phased clause that requires mediation or conciliation prior to arbitration may also be advisable. For manageable amounts and clear facts, this allows a dispute to be resolved more quickly and cost-effectively. However, this preliminary stage must include a fixed deadline after which arbitration proceedings can be initiated; otherwise, it will only delay the enforcement of the final invoice.

Conclusion

There are good reasons to include an arbitration clause in the main contract with a foreign end customer. Further down the chain, however, it often no longer serves its purpose. If the contracting party is based in Germany or the EU, the subcontractor is left primarily with higher costs and the loss of a second-instance appeal, and the uniform procedure sought by the general contractor does not, on its own, achieve the desired alignment. Subcontractors and component manufacturers should therefore review the clause before signing and, where it is not appropriate, negotiate it. That is the work of LEGAL+: to draft contracts with an eye toward potential disputes and to manage disputes with an eye toward the business.

Negotiating and Enforcing Limitations of Liability — How You, as a Provider, Can Limit Your Risk

A valve fails. Not just any valve, but the control valve in a steam turbine plant that your company supplied as a component manufacturer. The damage to the valve itself amounts to 12,000 euros. But the turbine has come to a standstill, the production line behind it has come to a standstill, and the operator estimates its lost production at 800,000 euros—per week. After six weeks of downtime—during which a replacement valve is procured, installed, and the plant is restarted—a claim for damages of just under five million euros is on the table. All for a component that you supplied for 40,000 euros.

This is not a hypothetical example. It illustrates a typical risk in the machinery and plant engineering industry, where a single component can bring an entire plant to a standstill—and where the resulting damages can exceed the value of your own services many times over. Whether your company survives this scenario does not depend on the quality of your valve. It depends on what your contract says about liability.

This article describes how liability limitations work in mechanical engineering and plant construction, why they are vital for suppliers, where the legal boundaries lie—and how you, as a general contractor, subcontractor, or component manufacturer, can use contracts to limit your liability risk so that it remains manageable.

Why Limitations on Liability Are Vital in Plant Engineering

In many industries, liability limitations are a matter of convenience. They are negotiated because it is standard contractual practice, but in the event of a serious incident, the amounts involved rarely threaten a company’s survival. In plant engineering, however, the situation is different. Here, there is a structural imbalance between the value of the service provided and the damage that can result from an error.

A general contractor building a facility for ten million euros risks not only the cost of corrective work in the event of a failure, but also the operator’s loss of production, contractual penalties owed to the end customer, liquidated damages under its own supply contracts, and, in the worst case, personal injury. The subcontractor who performs a partial service for one million euros can be held liable for the failure of the overall project if his partial service was the cause. And the component manufacturer—as in the opening example—faces claims that could exceed its entire annual revenue.

This imbalance cannot be resolved through technical means. Even effective quality management does not completely eliminate this risk. It can only be resolved through a contractual arrangement—by imposing a limitation of liability that caps the provider’s risk at a calculable level.

In practice, however, it turns out that many providers have not limited their liability—or have not limited it sufficiently. Either because they accepted the client’s contract terms without carefully reviewing the liability clauses, or because they gave in during negotiations when the client insisted on an unlimited liability provision. Or—and this is the most common case—because they enforced their own liability limitation but failed to verify whether the wording would actually hold up in a real-world scenario.

The Tools: What a Limitation of Liability Can Achieve

An effective liability limitation is a system consisting of several provisions that work together to address the various aspects of liability risk.

The maximum liability amount — the cap

The best-known mechanism is the maximum liability limit, referred to in international contract practice as a “cap” or “limitation of liability.” It limits the provider’s total liability to a specific amount—typically a percentage of the contract amount.

The cap amount varies depending on the industry, project, and negotiating position. In plant engineering, caps ranging from fifty to one hundred percent of the contract amount are common. In the components business, where the disparity between the value of the delivery and the potential for loss is particularly pronounced, lower percentages are often sought—thirty or fifty percent, or sometimes a fixed amount. In FIDIC-based contracts, the cap is typically set at one hundred percent of the Accepted Contract Amount, although individual categories of loss may be capped separately.

What may sound trivial requires the utmost care in its wording. A cap that limits “the provider’s liability” without defining which claims it covers is open to interpretation in the event of a dispute. Does it cover only contractual claims or also tort claims? Does it cover both damages and contractual penalties, or only damages? Does it apply per claim or to the total of all damages incurred during the term of the contract?

For the provider, the answer is clear: The cap must be worded as broadly as possible. It should cover all claims by the contracting party arising from and in connection with the contract—whether contractual or non-contractual, including damages and contractual penalties, as well as direct and consequential damages. And it should serve as an overall cap on cumulative liability, not as a limit for individual incidents. A cap of one million euros per incident offers little protection if three or four incidents occur over the course of the project.

The Exclusion of Consequential Damages and Lost Profits

In addition to the cap, the exclusion of indirect damages—referred to in English as “indirect, consequential, and incidental damages”—is the second key element of the limitation of liability. It applies to the category of damages that typically accounts for the largest amounts in plant construction: loss of production, lost profits, consequential damages to third parties, and lost business opportunities.

The distinction between direct and indirect damages is less clearly defined in German law than in the Anglo-Saxon legal tradition. The German Civil Code (BGB) does not provide a definitive definition of “indirect damages.” Case law distinguishes between damage that typically and predictably results from a breach of duty and damage that occurs only under specific circumstances present in an individual case. Therefore, a contractual exclusion of “indirect damages” is not always interpreted by German courts in the same way as it would be by an English or American court.

For the provider, this means that the clause must specifically list the types of damages that are excluded—not just a general reference to “consequential damages,” but an explicit listing of lost profits, production losses, business interruption losses, loss of contracts with third parties, and similar items. The more specific the list, the lower the risk that a court will interpret the clause restrictively.

Clients often try to undermine this clause by including counter-exceptions. A common phrasing is: “The exclusion of consequential damages does not apply to damages resulting from gross negligence or willful misconduct.” This is acceptable in practice—after all, no one can effectively exclude intentional acts or bodily injury anyway. More problematic are formulations that also lift the exclusion for cases of “simple negligence in the breach of material contractual obligations.” This is because a breach of material contractual obligations—so-called cardinal obligations—constitutes virtually every case of liability in plant construction: Anyone who builds a plant that does not function has breached a material contractual obligation. An exception for cardinal obligations therefore largely undermines the exclusion of consequential damages unless it, in turn, is limited by the cap.

Differentiation Based on Degrees of Fault

The third element of a robust limitation of liability is the distinction based on degrees of fault. Not every breach of duty carries the same weight, and the law draws clear lines in this regard that the contract must respect.

Liability for intentional acts cannot be excluded—this is mandatory under Section 276(3) of the German Civil Code (BGB). Anyone who intentionally causes harm to their contractual partner is liable without limitation. This is also acceptable to the provider, as intentional harm is an absolute exception in contractual practice.

In cases of gross negligence, the situation is more nuanced. While liability for gross negligence cannot be completely excluded in individual contracts, its amount can be limited—by means of a cap. In general terms and conditions, however, an exclusion or limitation of liability for gross negligence is generally invalid (Section 309(7) of the German Civil Code (BGB) as an indication in commercial transactions pursuant to Section 307 BGB).

The real point of negotiation lies in the issue of slight negligence. This is where there is the greatest leeway, and where the most intense battles are fought in practice. The provider wants to limit its liability for damages caused by slight negligence to the cap and completely exclude consequential damages. The client wants the provider to be liable for all foreseeable damages, even if they result from slight negligence.

In a well-structured liability clause, this results in a tiered model: In cases of willful misconduct, the provider bears unlimited liability—this is mandatory. In cases of gross negligence, the provider is liable up to the cap amount, but without excluding any types of damages. In cases of slight negligence, both the cap and the exclusion of consequential damages apply, limited to the typically foreseeable damage. Personal injury is exempt from all limitations.

This tiered model is widely used in plant construction contracts, but it is rarely clearly defined. Instead, many contracts contain general provisions that lead to interpretation issues in the event of a dispute, or client terms and conditions that blur the distinction in favor of the client.

The Terms and Conditions Perspective: When the Client Does Not Allow for a Limitation of Liability

In practice, it is rarely possible to fully incorporate a provider’s own limitation of liability into the contract. In the reality of plant construction, it’s usually the other way around: The client presents its contract terms, and these contain no limitation of liability in favor of the contractor—or, worse yet, a liability provision that further exacerbates statutory liability: indemnification clauses that make the contractor liable for damages to third parties, strict liability for consequential damages, and an extension of liability to cover the entire project loss regardless of the contractor’s degree of fault.

This is where the review of general terms and conditions comes into play—and it works both ways.

On the one hand, Section 307 of the German Civil Code (BGB) protects the provider from unreasonably onerous liability clauses in the client’s general terms and conditions. Indemnification clauses that hold the provider liable even for damages caused by the client itself are generally invalid under case law. Clauses that extend the provider’s liability beyond the statutory limit—for example, through strict liability for consequential damages—deviate from the statutory framework and place an unreasonable burden on the provider. Furthermore, clauses that do not allow the service provider to limit the amount of its liability may also be invalid in individual cases if they result in a financial burden that threatens the provider’s continued existence.

Conversely, the review of general terms and conditions also limits a provider’s ability to largely exclude its own liability in its general terms and conditions. A provider who completely excludes liability for slight negligence in its own terms and conditions risks having that clause declared invalid if it concerns material contractual obligations. Case law requires that liability for the breach of cardinal obligations due to slight negligence remain in effect even in general terms and conditions—limited to typically foreseeable damages, but not completely excluded.

This has two practical implications for the provider.

First: If the client insists on its unlimited liability provision and the provider nevertheless accepts the contract, the situation is not hopeless. The client’s liability clauses are most likely general terms and conditions and are subject to content review. In the event of a dispute, the provider can argue that the unreasonable clauses are invalid, and they will be replaced by the statutory provisions—which in many cases are more favorable to the provider than the contractual terms.

The second consequence: Any provider who drafts its own limitation of liability must be aware of and respect the limits of the review of general terms and conditions. A clause that is too broadly worded is no better than no clause at all—it is worse, because it gives the provider a false sense of security that does not exist in the event of a dispute. A valid limitation of liability in general terms and conditions is one that limits liability for fundamental obligations in cases of slight negligence to foreseeable damages, leaves liability for gross negligence and willful misconduct unaffected, and expressly excludes personal injury.

Liability in the Project Chain: Looking Up and Down the Chain

In plant construction, no single provider stands alone. The general contractor is liable to the client and seeks recourse from its subcontractors. The subcontractor is liable to the general contractor and seeks recourse from its suppliers. The component manufacturer is liable to the subcontractor and, in the worst-case scenario, has no one to whom it can pass on the damages.

Back to top: Limiting Your Own Liability

Limiting liability toward your contracting party—the party that commissioned you—is the most obvious and important measure. It follows the principles described above: a cap, exclusion of consequential damages, and differentiation based on degrees of fault.

For the subcontractor and the component manufacturer, this presents a particular challenge that goes beyond a mere matter of negotiation. In many back-to-back contracts, the liability provisions of the main contract are incorporated into the subcontract on a blanket basis. This means: The subcontractor’s liability is governed by a clause negotiated for the relationship between the general contractor and the client—with a cap based on the contract amount of the main contract and with categories of damages tailored to the overall project, not to the subcontractor’s specific scope of work.

A subcontractor who performs a partial service worth 500,000 euros and whose liability—through a back-to-back reference — is based on the main contract with a contract value of ten million euros, has a cap of ten million euros, not 500,000. This is clearly inadequate. The subcontractor must therefore ensure that its liability limitation is governed independently in the subcontract—based on its own contract amount, not that of the main contract.

Equally important is the delimitation of liability on the merits. A component manufacturer that supplies a drive is liable for defects in the drive. It is not liable for the failure of the overall project if that failure is due to integration errors, faulty planning, or the failure of other components. This limitation must be specified in the contract, because without it, in the event of a dispute, the entire cost of the project’s losses will be shifted to the party presumed to be at fault—and the component manufacturer is in the weakest negotiating position when it comes to attributing the cause to another party.

Down: Protections in Supplier Contracts

Any supplier who has negotiated a liability limit as stated above must ask itself: What happens if the damage originates not with me, but with my supplier?

The answer depends on whether the contract with the supplier contains a liability provision that is compatible with your own upper liability limit. Compatible does not mean identical—it would be unrealistic to require every supplier to have the same upper liability limit that you yourself have accepted. However, there must be a recourse option that is also economically viable in the event of a serious incident.

Here’s a typical scenario: The subcontractor has agreed to a liability cap of one million euros with the general contractor. His supplier—who delivered the defective component—has limited liability in its own terms and conditions to the base order value, i.e., 50,000 euros. If damage occurs and the subcontractor has to pay the general contractor 800,000 euros, he can claim a maximum of 50,000 euros in recourse from his supplier. He is left to cover the difference of 750,000 euros.

This scenario can be avoided—but only if the supplier puts as much effort into drafting its supplier contracts as it does into negotiating the upper limit of its own liability. The supplier’s liability must be proportionate to the risk that its product may pose to the overall system. And the statutes of limitations must be aligned: Anyone who accepts a maximum warranty period of 24 months but has agreed to only a 12-month warranty in their supplier contracts has a gap that could lead to a complete loss of claims in the event of a recourse claim.

Common Negotiation Mistakes — and How to Avoid Them

In my practice, I see the same mistakes over and over again when negotiating liability limitations. Most of them can be traced back to three basic patterns.

Limit liability to the cap

Many providers focus all their negotiating efforts on the amount of the cap—and overlook the fact that the question of what types of damages the cap actually covers is just as important. A cap of 500,000 euros that covers only direct damages, while the client can additionally claim indirect damages, lost profits, and contractual penalties, does not protect the provider. The limitation of liability must be a comprehensive concept in which the cap, exclusions of damages, and differentiation based on fault work together.

Accepting exceptions that undermine the cap

No client accepts a liability cap without exceptions. This is understandable—personal injury and willful misconduct must be excluded, and in cases of gross negligence, an exception is often unavoidable. But some exceptions are worded so broadly that they effectively nullify the cap. An exception for “all claims arising from the breach of material contractual obligations”—that is, the cardinal obligations—covers virtually every liability case in plant construction, since the construction of a functioning plant is always a material contractual obligation. Such an exception renders the cap worthless.

The provider must therefore negotiate the exceptions just as carefully as the cap itself. The minimum requirement is that even in the event of a breach of fundamental obligations, liability is limited to foreseeable, typically occurring damages. And this amount must be quantified or at least objectively determinable—not merely an open-ended reference to what a court deems “foreseeable” in a particular case.

Do not adjust insurance coverage and liability limits

A liability cap and liability insurance share the same goal—limiting financial risk—but they operate at different levels. A liability cap limits the claim. Insurance covers the damages if a claim is made. Ideally, they complement each other: The cap is set below the insurance coverage limit, and the exceptions not covered by the cap—such as personal injury and gross negligence—are insured.

In practice, this coordination rarely occurs. The contract is negotiated by the sales or legal department, the insurance policy is purchased by the finance department, and no one checks whether the two are compatible. Anyone who has negotiated a cap of two million euros but has general liability insurance with a coverage limit of one million has a one-million-euro gap that must be financed from their own assets in the event of a claim. And anyone with product liability insurance that excludes performance-related damages and consequential damages—which is the case with many policies—is uninsured for precisely the category of damages that accounts for the largest amounts in plant engineering.

Conclusion

Liability is the core business risk—treat it as such

In plant engineering, prices are fiercely negotiated, deadlines are intensely debated, and specifications are haggled over in detail. The liability clause, on the other hand, is often treated as a legal footnote—just one item among many on page 67 of the contract that is accepted because the negotiations have already dragged on too long and the client insists on its terms.

This is a mistake that could threaten your company’s very existence in a crisis. That’s because the liability clause sets the upper limit on how much a single project can cost your company. Without a cap, there is no contractual upper limit. A poorly worded cap can fail precisely where it’s needed most in the event of a dispute. A cap that isn’t aligned with the supply chain creates a risk that ultimately falls on the supplier financially.

What’s needed is an attorney who doesn’t view the liability clause in isolation, but rather in conjunction with the contractual penalties, the performance guarantee, the warranty, and the project’s entire risk chain. A lawyer who reviews the clause for compliance with standard terms and conditions before the contract is signed, sets the right priorities during negotiations, and—in the event of a dispute—knows where the client’s clause is vulnerable. This combination of contract drafting and litigation is what defines LEGAL+—thinking about contracts with an eye toward potential disputes and managing disputes with an eye toward the business.