LEGAL+ NEWS

Good night, freedom of contract - Bundestag passes massive restrictions on freedom of contract

The Bundestag passes a massive restriction on contractual freedom. The Federal Ministry of Justice has thus prevailed with its plan to limit the terms of consumer contracts to a maximum of one year.

Read my article from September 6, 2019 on this now serious legislative proposal, especially with regard to the resulting highly questionable restrictions on contractual freedom.

You can download the draft law passed by the Bundestag here.

The bill to restrict freedom of contract

As I commented in my article from September 6, 2019, the (further) restriction on the possibility of concluding contracts with a commitment period of at least two years that has now been adopted represents a massive curtailment of contractual freedom. There is also no justification for this in the draft bill now before us. On the contrary, it reveals a considerable misunderstanding of freedom of contract and its positive significance for consumers and the economy. It also continues the political line of denying consumers their maturity. Significantly, the draft bill states:

“(…) In many areas where open-ended contracts used to be common, consumers are now often only offered contracts with a two-year term on good terms, which are automatically renewed if the consumer does not terminate them in good time. The restrictions on contract terms that were previously in place are no longer appropriate. The long contract commitment inhibits consumers from switching to another provider and thus competition. The contract extension clauses are overlooked or forgotten by consumers. By limiting the term to one year, shortening the automatic renewal period and providing a shorter notice period of one month, the aim is to give consumers more freedom of choice with regard to their contract. The aim is to strengthen the position of the contractual partner and promote competition. (…)”

Rating

The Federal Ministry of Justice should consider whether the law that has now been passed will actually achieve the opposite of what is supposedly intended. This is because the ban on longer terms massively restricts the previous options for drafting contracts. Whereas the parties involved were previously still able to agree on contracts tailored to their respective needs, the planned restrictions will in fact significantly limit competition and freedom of choice. The losers of the proposed legislation are therefore almost everyone involved. The “winners” are at best those consumers who “forget” notice periods. The worthiness of protecting this group seems highly questionable when you consider that those affected who have “forgotten” to terminate their contract after a two-year contract period had previously benefited from very attractive contract conditions in most cases. In future, thanks to this group of “forgetters”, the aforementioned attractive contract conditions will no longer be available to anyone.

Do you have any questions?

LATEST ARTICLES

Construction of building
Commercial law

Degree of completion of the work

The standards relating to the right to refuse acceptance (Section 640 (1) sentence 2 BGB, Section 12 (3) VOB/B) state that acceptance of the work may not be refused due to insignificant defects. There is no statement on the required degree of completion of the work as a prerequisite for acceptance.

However, the question of what degree of completion the work must have reached in order to be considered ready for acceptance is very important, particularly in the case of plant construction, which is usually very complex.

Read more "
Construction worker with construction level working on a sidewalk
Commercial law

Major deficiency in plant engineering

Answering the question of whether there is a significant defect is very difficult, especially in often very complex plant construction. The absence of major defects is the decisive prerequisite for acceptance. The latter has considerable legal and practical significance: the start of the warranty periods is regularly linked to this. In addition, the due date of a considerable part of the agreed remuneration generally depends on acceptance.

Read more "
Construction worker in protective uniform shaking hands with businessman in hardhat at construction
Commercial law

Formal acceptance under building law

Particularly in the case of complex (plant) construction projects, the contracting parties often agree – usually on the basis of the VOB/B – to carry out a so-called formal acceptance. The following article deals with the question of what such a formal acceptance is actually all about.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE