LEGAL+ NEWS

The hurdles to an individual contract are high: when is a provision "negotiated" and therefore not subject to the restrictions of GTC law?

GTC law, i.e. the law governing general terms and conditions, represents a restriction on contractual freedom because it limits the possibilities for freely and effectively structuring the content of contracts. If a provision is subject to GTC law, it must comply with the requirements of GTC law, otherwise it is invalid. In order to avoid the restrictions of GTC law, the contracting parties must have negotiated the provision in question.

The legal hurdles to such “negotiation” are very high:

Signing contract in cafe

Starting point: Section 305 (1) sentence 3 BGB

Section 305 (1) sentence 3 BGB expressly states that a negotiated contractual provision is not subject to the law on general terms and conditions:

“General terms and conditions do not exist if the terms of the contract have been negotiated in detail between the contracting parties.”

What is “negotiation”?

What “negotiation” means is not clear from the law. A now well-established case law of the Federal Court of Justice provides clarification. For example, a fairly recent ruling by the Federal Court of Justice from March 26, 2015 (AZ VI ZR 92/14) is quoted as follows:

[33] (1) According to the case law of the Federal Court of Justice , negotiation requires more than negotiation. Negotiation in this sense can only be said to have taken place if the user first negotiates the non-statutory core content contained in his general terms and conditions, i.e. the provisions that amend or supplement the essential content of the statutory provision, seriously puts the content of the contract up for negotiation and gives the negotiating partner freedom to protect its own interests with at least the real possibility of influencing the content of the contractual terms. He must therefore clearly and seriously declare his willingness to make the desired changes to individual clauses (BGH, judgments of March 20, 2014 – VII ZR 248/13, BGHZ 200, 326 para. 27; of November 22, 2012 – VII ZR 222/12, BauR 2013, 462 para. 10). The user must explain the relevant circumstances (BGH, judgment of April 3, 1998 – V ZR 6/97, NJW 1998, 2600, 2601). As a rule, such willingness is also reflected in recognizable changes to the pre-formulated text. At most, under special circumstances, a contract can also be considered the result of “negotiation” if, after thorough discussion, the draft remains in place (BGH, judgment of November 22, 2012 – VII ZR 222/12, loc. cit.; default judgment of January 23, 2003 – VII ZR 210/01, BGHZ 153, 311, 321 with further references). N.). Even if the text is amended, a clause only loses its character as a General Terms and Conditions if the subsequent amendment is made in such a way that it justifies treating it as an individual agreement made from the outset. This is not the case if the user has not granted the contractual partner any freedom of design even after conclusion of the contract and has not put the non-statutory core content of the clause at disposition and the parties reach an agreement on this basis with which the detrimental effect of the clause is merely mitigated (see BGH, judgment of March 7, 2013 – VII ZR 162/12, BauR 2013, 946 marginal no. 30 = NZBau 2013, 297).

The following key criteria can be inferred from the aforementioned statements of the BGH:

  • Negotiating is more than negotiating!
  • The person proposing a regulation must seriously question its content. This must include the non-statutory core content of the regulation. It is therefore not sufficient if there is a willingness to adapt something (insignificant) in the regulation.
  • The other contracting party must be granted recognizable – and demonstrable (!) – freedom of action to safeguard its interests.
  • If the original content remains in the end, “special circumstances” may justify the assumption that a negotiation nevertheless took place.

Conclusion

The requirements for the existence of a negotiation are significantly higher than is commonly assumed.

If possible, you should therefore avoid drawing up the first draft of a contract. Because then you are the “user” of the provisions contained therein, which means that the contractual partner benefits from the law on general terms and conditions. Conversely, it is better: because then you yourself are the protected party.

In any case, good negotiation documentation should be ensured so that the negotiation can be proven in the event of a dispute.

Do you have any questions?

LATEST ARTICLES

White collar crime.
Compliance

Guide to GmbH law: The duties and liability risks of the managing director of a GmbH

In the external relationship, only the GmbH is liable, which can indemnify its managing directors. However, this does not mean that external liability of the managing directors is excluded.

In addition to personal liability in the area of tax and social security law, the managing director may also be liable on the basis of his own contractual obligations, on the basis of an induced legal appearance, on the basis of (personal) culpability when concluding the contract and in tort.

For the aforementioned reasons, every managing director of a GmbH is urgently recommended to be familiar with the requirements for proper managing director activities.

Read more "
Timber frame house, real estate
Commercial law

Estimation of fictitious defect rectification costs

For some time now, a landmark decision by the Federal Court of Justice has clarified that the contractual claim for damages in lieu of performance pursuant to Sections 437 No. 3, 280, 281 BGB can be assessed on the basis of the “fictitious” defect rectification costs that are likely to be necessary but have not yet been incurred, see BGH ruling of 12.03.2021, Ref. V ZR 33/19. In practice, it is of particular relevance how the court called upon to decide in an individual case is to determine the amount of such fictitious damage costs.

Read more "
Europe
Commercial law

EUGH ruling “LKW Walter”

The possibility of being able to enforce one’s own rights as easily and quickly as possible in cross-border EU business transactions, which is very welcome in principle, has some pitfalls. The author’s experience shows that traders are often overwhelmed when they receive legally relevant mail from abroad. This is not least due to the fact that court documents received from abroad often do not meet the requirements of European law.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE