LEGAL+ NEWS
Answering the question of whether there is a significant defect is very difficult, especially in often very complex plant construction. The absence of major defects is the decisive prerequisite for acceptance. The latter has considerable legal and practical significance: the start of the warranty periods is regularly linked to this. In addition, the due date of a considerable part of the agreed remuneration generally depends on acceptance.
The following article deals with the criteria that are particularly important when assessing whether a significant defect is to be assumed.
General definition: Material defect
In principle, a material defect exists if a defect is so serious in terms of its nature and scope, but above all in terms of its effects, that the client cannot reasonably be expected to ultimately rely on warranty claims, taking into account objective aspects in relation to the use assumed in accordance with the purpose of the contract and the success achieved.
Question: Is it reasonable to refer to warranty rights?
In plant construction in particular, it is evident that it is not possible to achieve complete freedom from defects at the agreed time of acceptance. Accordingly, the materiality of a defect is reached less quickly in large-scale plant construction than in less complex work.
When assessing the question of whether the client may refuse acceptance due to significant defects, the circumstances of the individual case must always be assessed. In addition to the question of whether the client can reasonably be expected to refer to the defect rights, the question of whether a defect justifies denying the contractor all the benefits of acceptance should also be examined.
Restrictions in usability and safety deficiencies are usually to be regarded as significant defects
Restrictions on usability and safety defects are generally considered to be significant.
Here, even “minor” deviations may constitute a significant defect. For example, the Higher Regional Court of Düsseldorf (BauR 2004, 1668) has ruled that in the area of sound insulation, a negative deviation of 3dB can be sufficient to justify a significant defect.
With regard to the usability of the delivered work, it must be taken into account that its impairment must be assessed all the more highly – and thus all the more likely as a significant defect – if warranted characteristics are not fulfilled, as the client has attached particular importance to these.
Number of existing defects significant?
Even if it cannot be automatically concluded from the mere number of defects that the service is not suitable for acceptance, the sum of individually insignificant defects can certainly result in a right to refuse acceptance. In this respect, in individual cases, several minor defects added together may be equivalent to a major defect.
Amount of the defect rectification costs
Finally, the (total) costs of remedying the defect must also be taken into account when assessing materiality.
The higher the total cost of remedying existing defects, the more likely it is that the materiality criterion will be met.

Conclusion: Significant deficiency
The above illustration shows that the question of whether a material defect exists is largely a question of judgment. In practice, it has repeatedly proved helpful to answer the question of whether the defect in question justifies denying the contractor the essential legal consequences of acceptance.

LATEST ARTICLES

Guide to International Civil Procedure: Recognition and enforcement of foreign judgments in Germany
Once a judgment has been successfully obtained against a German debtor abroad (in a third country), the creditor is faced with the important practical question of how to actually get his money.
If the German debtor does not pay voluntarily, only the enforcement of the judgment will help. However, since in most cases the German debtor only has assets in Germany that could be enforced, the foreign judgment must be enforced in Germany. This requires that the foreign judgment has first been declared enforceable by a German court. This declaration of enforceability is the subject of separate court proceedings against the debtor in Germany, at the end of which, if successful, an enforcement order will be issued.
The following article deals with the content of these proceedings.

Guide to appeal law – Importance of the content of the grounds of appeal for the scope of review by the court of appeal
The view that the content of the grounds of appeal determines the scope of review by the court of appeal is widespread. According to this view, the grounds of appeal must contain all complaints regarding the first instance judgment that the appellant wishes to have reviewed by the court of appeal. If the appellant omits a complaint, this would mean that the court of appeal itself would have to ignore legal violations that it has recognized and deemed to be significant.

Possibilities of contesting a settlement concluded in court
Civil proceedings are often concluded by way of a settlement between the parties during the course of the proceedings. This is often done with the help of the court. Practice shows that such a settlement, despite the involvement of the court, is not without its pitfalls. I would like to provide an overview below.
CONTACT

+49 (40) 57199 74 80
+49 (170) 1203 74 0
Neuer Wall 61 D-20354 Hamburg
kontakt@legal-plus.eu
Benefit from my active network!
I look forward to our networking.
This post is also available in: DE