Estimation of fictitious defect rectification costs

LEGAL+ NEWS

BGH ruling of March 11, 2022 - V ZR 35/21: Criteria for the judicial estimation of fictitious defect rectification costs

Problem definition

It has been clarified for some time by a landmark decision of the BGH that the contractual claim for damages instead of performance in accordance with Sections 437 No. 3, 280, 281 BGB can be assessed on the basis of the “fictitious” costs of remedying defects that are likely to be necessary but have not yet been incurred, see BGH ruling of 12.03.2021, Ref. V ZR 33/19.

In practice, it is of particular relevance how the court called upon to decide in an individual case is to determine the amount of such fictitious damage costs. The starting point for this is Section 287 (1) ZPO, which reads as follows:

“If there is a dispute between the parties as to whether damage has occurred and how much the damage or an interest to be compensated amounts to, the court shall decide on this in its own discretion, taking into account all the circumstances. Whether and to what extent a requested taking of evidence or ex officio expert appraisal is to be ordered is left to the discretion of the court. (…)”

It has not yet been clarified according to which principles the court must apply the aforementioned Section 287 (1) ZPO in the specific case.

In a more recent decision from March 11, 2022 (case no. V ZR 35/21), the BGH provided the courts of lower instances with valuable criteria.

Construction worker with construction level working on a sidewalk

The judgment

Its decision of March 11, 2022 (case no. V ZR 35/2) was based on the following abridged facts:

The subject of the dispute was the purchase contract for a property. The sellers had concealed from the buyers that the external waterproofing of the cellar was incomplete and accordingly demanded compensation in the form of fictitious defect rectification costs.

The court of first instance had sentenced the defendants in the amount of fictitious defect rectification costs of EUR 144,800. The Court of Appeal reduced this amount to EUR 97,556 and allowed the appeal with regard to the amount of the claim.

The estimate made by the court of first instance and the court of appeal was based on an expert opinion, according to which two options for remedying the defects could be considered. According to the less expensive option A, the incompleteness of the waterproofing could not be completely eliminated, according to the more expensive option B with costs of EUR 138,920, waterproofing would be completely possible. The Court of Appeal assumed that the plaintiffs did not have to be satisfied with variant A, however, the estimation inaccuracy of +/- 30% mentioned by the expert was to be taken into account to their detriment, as the plaintiffs could only be awarded whatwouldcertainly be incurred” in terms of defect rectification costs. Uncertainties in determining the costs of remedying defects should not be borne by the tortfeasor.

In its decision, the BGH initially confirmed the Court of Appeal’s assumption that the claimants did not have to settle for the cheapest option. The same applies to the rejected “new for old” deduction.

Otherwise, however, it rejected the Court of Appeal’s assumptions for determining the specific amount of damages as legally untenable. The BGH stated:

“As a starting point, the Court of Appeal correctly assumes that the contractual claim for damages instead of performance (minor damages) pursuant to Sections 437 No. 3, 280, 281 BGB can be assessed on the basis of the “fictitious” costs of remedying defects that are likely to be necessary but have not yet been incurred.

However, according to the reasoning of the Court of Appeal, the costs for the necessary renovation work determined by the expert cannot be reduced by 30% when assessing the amount of the claim for damages.

The court must determine the amount required to rectify the defect in accordance with Section 287 (1) ZPO, taking into account all the circumstances in its own discretion.

(…)

The Court of Appeal overstretches the measure of necessary conviction within the framework of Section 287 (1) ZPO and thus disregards legal principles of damage assessment.

If the asserted claim for damages is established on the merits and only the amount needs to be filled in, the injured party benefits from the facilitation of evidence under Section 287 ZPO. In contrast to the strict requirements of Section 286 (1) ZPO, when deciding on the amount of damages, a considerable probability based on a sound foundation is sufficient for the court to form its opinion; the estimate should be as close as possible to reality.

The court of appeal misjudged this. It believes that only the amount that is certain to be incurred within the scope of the estimate to be made for the rectification of defects may be awarded, so that in the case of a range of estimates, only the lower amount can regularly be awarded as damages. It thus wrongly demands absolute certainty for the assessment of damages to be carried out by it, which is not even required within the framework of § 286 ZPO. It is true that even in the case of an estimate pursuant to Section 287 ZPO, doubts about the amount of the costs required to remedy the defect may not, in principle, be borne by the tortfeasor (see BGH, Urt. v. 10.04.2003 – VII ZR 251/02NJW-RR 2003, 878, 879; OLG Celle, Urt. v. 17.01.2013 – 16 U 94/11BauR 2014, 134, 139). However, it is in the nature of things that when calculating the fictitious restoration costs required to remedy the damage, a (certain) uncertainty remains as to whether the amount objectively required for the repair (to be assessed ex ante) corresponds to the amount that would have been or would be incurred if the repair had actually been carried out. If the contractual claim for damages in lieu of performance (small damages) pursuant to Sections 437 No. 3, 280, 281 BGB is assessed on the basis of the presumably necessary but not (yet) incurred (“fictitious”) costs of remedying the defect, the court must therefore determine the damage in accordance with the principles of Section 287 (1) ZPO and in this respect to examine the extent to which damage is predominantly probable. This also and especially applies if a range of estimates is stated in an expert report. (…)”

As a consequence of the aforementioned deficiencies, the BGH referred the case back to the Court of Appeal for reconsideration and decision

Conclusion

With this decision, the BGH first confirmed that Section 287 ZPO is decisive for determining the fictitious amount of damages. For the formation of a judicial conviction, a

“considerable probability based on a sound foundation.”

Any remaining uncertainty lies in the nature of the simplified assessment of damages pursuant to Section 287 ZPO. It follows for the courts of lower instances that it is not permissible to assume the minimum amount specified by the expert as the damage. The court must correctly approach the most probable amount required to remedy the defect. For claimants, this means that it may be advisable to consult their own expert to help determine the “probable costs”.

Construction worker with construction level working on a sidewalk
Do you have any questions?

LATEST ARTICLES

truck on a highway through the grasslands area of eastern Washington, USA.
Transportation law

To obtain a road haulage license in Germany

The road haulage industry is subject to licensing for transports with motor vehicles with a gross vehicle weight of over 3.5 tons. The requirements to be met to obtain a road haulage license are outlined below.

Read more "
Skyline of Frankfurt / Main in Germany with the European Central Bank on the Right side.
Commercial law

EURO clauses – prevention of euro crisis scenarios

The term “euro clause” is still predominantly associated with the introduction of the euro. The following article deals with the unpleasant eventuality of the euro entering a crisis, e.g. associated with the exit of individual countries from the eurozone. To prevent this eventuality, it is worth thinking about “post-euro” clauses.

Read more "
Concept of signing to sign a contract.
Commercial law

Agreement of obligations to keep free

The contractual agreement of hold harmless obligations is still a rarely used contractual instrument. However, such indemnity agreements can be very helpful, especially in multi-party constellations. One particularly relevant example is in the area of highly complex and therefore contentious plant construction.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE