LEGAL+ NEWS

Degree of completion of the work as a prerequisite for acceptance

Acceptance of a work may not be refused due to insignificant defects (Section 640 (1) sentence 2 BGB, Section 12 (3) VOB/B). There is no statement in the relevant standards regarding the required degree of completion of the work as a prerequisite for acceptance.

However, the question of what degree of completion the work must have reached in order to be considered ready for acceptance is very important, particularly in the case of plant construction, which is usually very complex. This is because, from a strict point of view, complete completion is unlikely to be achievable due to the technical complexity of many plant construction projects or, from the plant constructor’s point of view, will only be achieved at a point in time that is hardly acceptable.

The following article provides information on the extent to which the degree of completion affects the right to acceptance.

Principle: Acceptance only when the work is fully completed and finished

In private construction law, the principle applies that acceptance can only be considered if the work is fully completed and finished on the acceptance date.

Restrictions of this principle by supreme court rulings

In some older decisions, the BGH expressly differentiated between a defective and an unfinished work. According to the BGH, acceptance could only be considered when the work is completed, even if it still has defects (BGH NJW 1964, 647; BGH NJW 1979, 650).

On the other hand, the BGH had already determined at that time that, although acceptance could only be considered upon completion, it was nevertheless possible if individual services were still outstanding (BGH BauR 1973, 192).

In more recent decisions, the BGH has become clearer. In its opinion, it does not prevent the contractor from demanding acceptance if insignificant remaining work is still missing, which is irrelevant for the customer’s decision as to whether he wishes to accept and approve the performance as fulfillment (BGH NJW 2000, 2818, 2819). Outstanding minor remaining work that is insignificant for the usability of the work would not prevent acceptance.

In the literature, it is also generally assumed that the contractor’s claim is not precluded by the fact that insignificant remaining services are still missing, which are insignificant and unimportant for the client’s decision as to whether he wants to accept and approve the service as fulfillment.

Construction of building

Conclusion on the required degree of completion

After all, it can be regarded as established law that the actual complete performance of the work is not a prerequisite for readiness for acceptance, but that insignificant residual work may still be missing.

Whether outstanding work is to be regarded as essential or immaterial is – as with the determination of the materiality of a defect – a question of the individual case.

As a rule of thumb , you as a plant manufacturer can remember the required degree of completion as a prerequisite for acceptance:

Remaining work that is still open and can be classified as insignificant does not prevent acceptance.

Do you have any questions?

LATEST ARTICLES

Businessmen Deal Handshake Agreement Concept
Commercial law

Corona as a disturbance of the business basis?

Since the beginning of the coronavirus crisis, countless contractual relationships have not been able to be implemented as planned. The government corona measures, for which none of the contracting parties are naturally responsible, were mostly to blame. This has raised the exciting question of how to deal with cases in which the main contractual service – e.g. the provision of the premises in tenancy law constellations – could still be provided despite the corona measures, but the tenant was unable to use the premises in whole or in part as a result of the corona measures.

Read more "
collection of various flags of different countries standing tall together in a row on a stand
Nicht kategorisiert

Action from abroad – service effective?

Being sued is always unpleasant. However, if you have to deal with a lawsuit from abroad, the annoyance is considerably greater for various reasons, just to mention the often considerable costs. The first question you should ask yourself when you find a claim from abroad in your letterbox is: Is service of the claim effective at all? This is often not the case, which brings you various advantages (e.g. saving time, possibility of taking your own procedural steps, etc.).

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE