Degree of completion of the work as a prerequisite for acceptance

Acceptance of a work may not be refused due to insignificant defects (Section 640 (1) sentence 2 BGB, Section 12 (3) VOB/B). There is no statement in the relevant standards regarding the required degree of completion of the work as a prerequisite for acceptance.

However, the question of what degree of completion the work must have reached in order to be considered ready for acceptance is very important, particularly in the case of plant construction, which is usually very complex. This is because, from a strict point of view, complete completion is unlikely to be achievable due to the technical complexity of many plant construction projects or, from the plant constructor’s point of view, will only be achieved at a point in time that is hardly acceptable.

The following article provides information on the extent to which the degree of completion affects the right to acceptance.

Principle: Acceptance only when the work is fully completed and finished

In private construction law, the principle applies that acceptance can only be considered if the work is fully completed and finished on the acceptance date.

Restrictions of this principle by supreme court rulings

In some older decisions, the BGH expressly differentiated between a defective and an unfinished work. According to the BGH, acceptance could only be considered when the work is completed, even if it still has defects (BGH NJW 1964, 647; BGH NJW 1979, 650).

On the other hand, the BGH had already determined at that time that, although acceptance could only be considered upon completion, it was nevertheless possible if individual services were still outstanding (BGH BauR 1973, 192).

In more recent decisions, the BGH has become clearer. In its opinion, it does not prevent the contractor from demanding acceptance if insignificant remaining work is still missing, which is irrelevant for the customer’s decision as to whether he wishes to accept and approve the performance as fulfillment (BGH NJW 2000, 2818, 2819). Outstanding minor remaining work that is insignificant for the usability of the work would not prevent acceptance.

In the literature, it is also generally assumed that the contractor’s claim is not precluded by the fact that insignificant remaining services are still missing, which are insignificant and unimportant for the client’s decision as to whether he wants to accept and approve the service as fulfillment.

Construction of building

Conclusion on the required degree of completion

After all, it can be regarded as established law that the actual complete performance of the work is not a prerequisite for readiness for acceptance, but that insignificant residual work may still be missing.

Whether outstanding work is to be regarded as essential or immaterial is – as with the determination of the materiality of a defect – a question of the individual case.

As a rule of thumb , you as a plant manufacturer can remember the required degree of completion as a prerequisite for acceptance:

Remaining work that is still open and can be classified as insignificant does not prevent acceptance.

Do you have any questions?

LATEST ARTICLES

collection of various flags of different countries standing tall together in a row on a stand
International procedural law

Guide to International Civil Procedure: Recognition and enforcement of foreign judgments in Germany

Once a judgment has been successfully obtained against a German debtor abroad (in a third country), the creditor is faced with the important practical question of how to actually get his money.

If the German debtor does not pay voluntarily, only the enforcement of the judgment will help. However, since in most cases the German debtor only has assets in Germany that could be enforced, the foreign judgment must be enforced in Germany. This requires that the foreign judgment has first been declared enforceable by a German court. This declaration of enforceability is the subject of separate court proceedings against the debtor in Germany, at the end of which, if successful, an enforcement order will be issued.

The following article deals with the content of these proceedings.

Read more "
Entrance to the Royal Court of Justice
Nicht kategorisiert

Guide to appeal law – Importance of the content of the grounds of appeal for the scope of review by the court of appeal

The view that the content of the grounds of appeal determines the scope of review by the court of appeal is widespread. According to this view, the grounds of appeal must contain all complaints regarding the first instance judgment that the appellant wishes to have reviewed by the court of appeal. If the appellant omits a complaint, this would mean that the court of appeal itself would have to ignore legal violations that it has recognized and deemed to be significant.

Read more "
Vertragsgestaltung im Vertragsrecht – klare Regelungen
Contract Law

Possibilities of contesting a settlement concluded in court

Civil proceedings are often concluded by way of a settlement between the parties during the course of the proceedings. This is often done with the help of the court. Practice shows that such a settlement, despite the involvement of the court, is not without its pitfalls. I would like to provide an overview below.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE