Remuneration for "additional" services in flat-rate contracts

The remuneration for “additional services” in lump-sum price contracts in the event of supplementary offers from the contractor is complex. In principle, the additional remuneration demanded as a result of the supplement must be derived from the (plant) construction contract concluded between the parties. If this is a lump-sum price contract, it often depends on the details of the agreed scope of services that are to be owed at the agreed lump-sum price.

The following article is intended to help those affected who have concluded a VOB/B lump-sum price contract to determine whether or not they are entitled to (additional) remuneration in a specific case.

construction area

VOB/B principle: No entitlement to remuneration other than the lump sum price

According to § Section 2 (7) sentence 1 VOB/B changes to the contractually agreed price are generally excluded. This means that the client can generally rely on not having to pay more than the agreed total fixed price for the contracted service.

VOB/B exceptions

According to VOB/B, there are the following exceptions to the principle that the lump sum price cannot be changed:

  • Unreasonableness of adhering to the lump sum price pursuant to Section 2 (7) No. 1 Sentence 2 VOB/B in conjunction with Section 313 BGB
  • Remuneration for additional or modified services in accordance with § 5 in conjunction with § 2 Para. 7 No. 2, § 2 Para. 5, 6 VOB/B
  • Subsequent recognition of a service not commissioned by the client pursuant to Section 2 (8) no. 2 sentence 1 VOB/B
  • Management without a contract pursuant to Section 2 (8) no. 2 sentence 2, no. 3 VOB/B in conjunction with Sections 677 et seq. BGB

The first two cases deserve special attention:

Unreasonableness of adhering to the flat-rate price

Even in the case of lump-sum prices, the originally agreed price can be changed in accordance with Section 2 (7) No. 1 Sentence 2 VOB/B if the work performed deviates so significantly from the planned work that it is no longer reasonable for one of the parties to adhere to the lump sum. In this case, the unreasonable burden is compensated by granting the additional or reduced costs.

The standard for unreasonableness is derived from Section 313 BGB, the disturbance of the basis of the transaction. This requires a blatant disproportion between the service and the lump sum. Extremely strict requirements are set and an assessment is made depending on the individual case.

The contractor bears the risk for the correct calculation when agreeing a lump sum price; if he could have recognized that his service description was incorrect or incomplete, he cannot subsequently invoke an unreasonable lump sum price. If a “fixed price” has been agreed, there are particularly high hurdles for the contractor to prove an unreasonable burden.

Remuneration for “additional” or “modified” services

A claim to remuneration that can be demanded in addition to the agreed lump sum price is granted by § 2 Para. 7 No. 2 VOB/B, according to which the provisions of § 2 Para. 5, 6 VOB/B (remuneration for additional or changed services) also apply if a lump sum has been agreed.

The decisive factor here is whether the service is actually an “additional” or “modified” service.

This is only the case if the service is not already included in the originally agreed service target. It is disputed who bears the burden of proof that the service is not part of the original performance target.

This question is always determined by what the parties have specifically agreed:

Systematically, a distinction is made between a global flat-rate contract and a detailed flat-rate contract. In practice, there are a large number of mixed forms, so that classification into a pure contract type appears to be rather unusual. However, the classification can provide arguments as to whether a certain service is already contractually owed or not. For the distinction between global flat-rate contracts and detailed flat-rate contracts, please read my separate CONTRIBUTION. The following are therefore only the key points:

Global flat-rate contract

In a global lump sum contract, the service is described functionally and the contractor bears the particular risk of having to supplement the original rough service description in any case.

Detailed flat-rate contract

In a detailed flat-rate contract, on the other hand, it is not the service that is flat-rate but the price. This contract is usually based on a detailed specification of services. The flat-rate price then only includes the services described in the specifications.

Contracts with a so-called completeness clause

In the case of so-called all-inclusive clauses, according to which the contractor is obliged to provide all necessary services without separate remuneration, it depends, according to case law, on who is to bear the risk of unforeseeable services. In the case of detailed flat-rate contracts, the risk should be limited to increased quantities; completely new services should not be borne by the contractor.

Summary

Whether remuneration for “additional services” is justified in the case of lump-sum price contracts is primarily determined by whether the service in question, for which additional remuneration is demanded, exceeds the originally agreed service target. If this is not the case, additional remuneration may only be justified in rare exceptional cases.

After all, the agreement of the scope of services owed in (plant) construction contracts is of paramount importance. Experience has shown that it is advisable to determine the scope of performance with the utmost care and in as much detail as possible. In the event of a dispute, it can be of decisive importance to have avoided scope for interpretation wherever possible.

Construction
Do you have any questions?

LATEST ARTICLES

Present your case...Serious young judge sitting in the courtroom with a stern facial expression.
Nicht kategorisiert

The court’s duty to provide information in civil proceedings

It is not uncommon for courts to simply remain silent until the first hearing date – in the worst case, years can pass until then. As a result, the parties do not know where they stand for a long time and eagerly await the hearing date, from which they hope to finally learn the court’s point of view. It is often only during the court hearing that judges then issue so-called judicial instructions in accordance with Section 139 (2) and (3) ZPO. This procedure is unlawful!

Read more "
Plenty of space on this one. An african-american woman showing you a USB stick.
Nicht kategorisiert

Reference to USB stick in the application

Our latest article analyzes the BGH ruling of 14.07.2022, which for the first time allows reference to a USB stick in the claim. Find out how this ruling expands the scope of digitalization in civil proceedings and what consequences it has for practice.

Read more "
Gavel, scales of justice and law books
Nicht kategorisiert

Action dismissed as “currently unfounded”

Disputes under construction law in particular often concern the due date of remuneration claims, e.g. because acceptance as a prerequisite for payment is questionable. In these cases, it is not uncommon for judgments to be handed down in which a claim is dismissed “as currently unfounded”.

The BGH recently stated in detail that in such cases the res judicata effect of the dismissing judgment also includes the grounds for the judgment, insofar as the other – i.e. the currently not missing – claim requirements have been positively established or affirmed.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE