Documentary action in civil proceedings: definition, procedure and context with the order for payment procedure

LEGAL+ NEWS

Documentary action in civil proceedings: definition, procedure and context with the order for payment procedure

This guide explains the document action in German civil proceedings, its differences to the dunning procedure and gives tips on when it makes sense.

What is a document action?

An action based on documentary evidence or a documentary process offers the possibility, as an accelerated procedure, to bring an action – initially – only by means of documents, see Section 592 ZPO.

Consequently, no witnesses are heard and no expert opinions are prepared in the so-called documentary proceedings. Only the claim arising from the document is examined. The defendant’s defense options are limited to documents. The latter means:

Even if the claim asserted by means of documents is unfounded, but the defendant cannot prove this by means of documents, the plaintiff will initially win the documentary proceedings and thus obtain a – provisionally – enforceable title.

However, the defendant then has the opportunity to raise all objections to the claim that he was denied in the documentary proceedings in so-called subsequent proceedings (Section 600 ZPO). In the event of success, the plaintiff, who has taken enforcement measures on the basis of the title obtained in the documentary proceedings, is obliged to pay damages to the defendant.

Documentary action vs. dunning procedure

The documentary process described above should be seen in conjunction with the dunning procedure. Both procedures represent an opportunity to obtain an enforcement order in a significantly shorter time compared to a regular lawsuit.

While an unfounded objection by the defendant in dunning proceedings simply leads to the plaintiff having to pursue his claim further in regular legal proceedings, the action for documentary evidence offers the opportunity to obtain an enforcement order by means of a document that suitably securitizes the claim in question. An objection by the defendant alone is therefore not sufficient. Only if the defendant succeeds in overturning the merits of the claim on the basis of the document must the plaintiff – as in the case of the dunning procedure – pursue his claim further in regular legal proceedings.

Law, portrait and a mature graduate with a certificate from education achievement in an office. Smi

Assessment: When is an action for documentary evidence the right procedure for you?

The action on documentary evidence is intended to speed up the proceedings, but can only fully exploit its advantages if the claim clearly emerges from the document and the defendant does not raise any substantiated objections. Otherwise, the proceedings can – or rather: will – turn into regular legal proceedings (subsequent proceedings) with the result that the plaintiff should have opted for the normal proceedings from the outset.

Even if the legal requirements for bringing an action for documentary evidence are met, this is therefore not always the best choice.

In particular, the plaintiff is advised to anticipate the defendant’s potential resistance in advance and to plan accordingly. If the defendant’s resistance seems likely, it makes more sense in case of doubt to opt directly for regular legal proceedings in order to save time and resources.

However, before choosing this method, the specific facts of the case should always be considered and the advantages and disadvantages weighed up.

Do you have any questions?

LATEST ARTICLES

Construction of building
Commercial law

Degree of completion of the work

The standards relating to the right to refuse acceptance (Section 640 (1) sentence 2 BGB, Section 12 (3) VOB/B) state that acceptance of the work may not be refused due to insignificant defects. There is no statement on the required degree of completion of the work as a prerequisite for acceptance.

However, the question of what degree of completion the work must have reached in order to be considered ready for acceptance is very important, particularly in the case of plant construction, which is usually very complex.

Read more "
Construction worker with construction level working on a sidewalk
Commercial law

Major deficiency in plant engineering

Answering the question of whether there is a significant defect is very difficult, especially in often very complex plant construction. The absence of major defects is the decisive prerequisite for acceptance. The latter has considerable legal and practical significance: the start of the warranty periods is regularly linked to this. In addition, the due date of a considerable part of the agreed remuneration generally depends on acceptance.

Read more "
Construction worker in protective uniform shaking hands with businessman in hardhat at construction
Commercial law

Formal acceptance under building law

Particularly in the case of complex (plant) construction projects, the contracting parties often agree – usually on the basis of the VOB/B – to carry out a so-called formal acceptance. The following article deals with the question of what such a formal acceptance is actually all about.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Bleichenbrücke 11 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE