Contract law: For the drafting of contracts in construction law - especially in plant construction

In construction law, especially in the area of plant construction, the general contractor regularly commissioned assumes very considerable risks. A charming way for them to limit these risks can be to pass on contracts or individual relevant contractual terms to their subcontractors.

In this case, the general contractor agrees with each of its subcontractors that all obligations arising from the general contractor agreement (main contract), insofar as they relate to the subcontractor’s work, will be “passed on” to the subcontractor. The general contractor thus passes on the relevant obligations 1:1 to its subcontractors.

The following article deals with the legal framework conditions of such a contract construction by means of the interposition of contracts, in particular with the question of the extent to which there could be concerns about the effectiveness of such a construction.

Fundamental permissibility of such a contractual arrangement

Contracts with subcontractors (subcontractor contracts) are generally independent construction contracts from which the rights and obligations arise independently of the main contract (Junghenn, Beck VOB-Kommentar, Part B, 3rd edition 2013, para. 24).

The transfer of the general contractor’s obligations towards the client arising from the main contract to subcontractors is, in principle, a legally possible contractual constellation that is used in practice:

This possibility arises, for example, from the VOB/B, regulated in § 4 para. 8: According to this, the contractor must provide the service in his own company, but he can also commission subcontractors without the consent of the client if the specific service does not fall within his area of expertise.

The latter is probably the rule, especially in plant construction. It is rare for a general contractor to have all of the necessary specialist skills for the construction of complex plants.

It is also a recognized option for the general contractor to outsource its work services in their entirety to subcontractors (Junghenn, Beck VOB-Kommentar, Teil B, 3rd edition 2013, para. 8). The general contractor then assumes a kind of intermediary function (Klaus Ramming: Überlegungen zur Ausgestaltung von Nachunternehmerverträgen durch AGB, BB 1994, Heft 8, 518).

Irrespective of this, the contractor and subcontractors can agree on provisions in the subcontractor contract that are identical in content and run in parallel to those found in the legally independent main contract between the contractor and its client; the contractor (often as a general contractor), which sits “between the two chairs” of client and subcontractor, inevitably has a justified interest in the parallel connection (synchronicity) of important provisions of the general contractor contract on the one hand and the subcontractor contract on the other (Junghenn, Beck VOB-Kommentar, Teil B, 3. Edition 2013, para. 24).

Finally, it is also legally possible to pass through provisions of the main contract by simple reference (Richter in Messerschmidt/Voit, Privates Baurecht, 2nd edition 2012, para. 238). This applies in any case to the synchronization of performance obligations (Kimmich/Bach VOB für Bauleiter, 6th edition 2014, para. 408).

Ineffectiveness in individual cases after GTC review

The only remaining problem in this context could be that the reference to the provisions of the main contract could lead to the application of GTC law in the respective individual case and thus to the possible invalidity of individual clauses.

If the inclusion of the provisions of the main contract in the subcontractor contract has not been negotiated, the law on general terms and conditions is likely to apply as a rule.

An ineffectiveness under GTC law can be considered, for example, when clauses on limitation periods, extraordinary termination rights and due dates are passed on (cf. compilation by Richter in Messerschmidt/Voit, Privates Baurecht, 2nd edition 2012, para. 240- 246).

Important: The provision of performance obligations is unobjectionable under GTC law!

However, with regard to the probably most important and at the same time most liable clause, namely the passing on of performance obligations, there are generally no concerns about effectiveness.

The reference to the main contract regarding the performance obligations should not constitute a GTC provision. In addition, such a reference should also be unobjectionable under GTC law.

The performance obligations regulated in the main contract do not generally constitute GTCs themselves, as these are always agreed individually between the client and the general contractor. This individual agreement also does not become GTC if it is agreed with several subcontractors by reference.

In any case, a review of the general terms and conditions with regard to the scope of services only takes place to a limited extent. It is limited to a pure transparency check, a content check does not take place.

Construction

Conclusion

Passing on contracts of the general contractor to subcontractors is permissible without any problems in the case of individual agreements.

In the case of general terms and conditions, problems may arise with the passage of individual clauses. However, this does not generally apply to the inclusion of the service description.

Do you have any questions?

LATEST ARTICLES

White collar crime.
Compliance

Guide to GmbH law: The duties and liability risks of the managing director of a GmbH

In the external relationship, only the GmbH is liable, which can indemnify its managing directors. However, this does not mean that external liability of the managing directors is excluded.

In addition to personal liability in the area of tax and social security law, the managing director may also be liable on the basis of his own contractual obligations, on the basis of an induced legal appearance, on the basis of (personal) culpability when concluding the contract and in tort.

For the aforementioned reasons, every managing director of a GmbH is urgently recommended to be familiar with the requirements for proper managing director activities.

Read more "
Timber frame house, real estate
Commercial law

Estimation of fictitious defect rectification costs

For some time now, a landmark decision by the Federal Court of Justice has clarified that the contractual claim for damages in lieu of performance pursuant to Sections 437 No. 3, 280, 281 BGB can be assessed on the basis of the “fictitious” defect rectification costs that are likely to be necessary but have not yet been incurred, see BGH ruling of 12.03.2021, Ref. V ZR 33/19. In practice, it is of particular relevance how the court called upon to decide in an individual case is to determine the amount of such fictitious damage costs.

Read more "
Europe
Commercial law

EUGH ruling “LKW Walter”

The possibility of being able to enforce one’s own rights as easily and quickly as possible in cross-border EU business transactions, which is very welcome in principle, has some pitfalls. The author’s experience shows that traders are often overwhelmed when they receive legally relevant mail from abroad. This is not least due to the fact that court documents received from abroad often do not meet the requirements of European law.

Read more "

CONTACT

LEGAL+

+49 (40) 57199 74 80

+49 (170) 1203 74 0

Neuer Wall 61 D-20354 Hamburg

kontakt@legal-plus.eu

Benefit from my active network!

I look forward to our networking.

Copyright 2025 © All rights reserved.

This post is also available in: DE